Current Projects

COVB Airport logo

Current Projects - Updated - February 2019

  •  North Ramp Rehabilitation

Construction underway; estimated completion by September 2019.

  •  Construct Taxiway E Extension

 Construction underway; estimated completion by September 2019.

  •  Airport Security Improvements

Design is complete and contractor has been selected an awarded the contract. Work will start in March 2019.

  • Rehabilitate T-Hangar Buildings

Roof rehabilitation completed

Additional work to repair several hangar doors will be advertised for contractors by May 2019.

  • Construct MRO Hangar 

State funding in place. Lease negotiation in progress; estimated start of construction: September 2019.

  • Reconstruct Center Apron

Requesting grant funding from the State of Florida to begin design for this project. Estimate start of construction: April 2020 (after the Vero Beach Air Show).