Current Projects - Updated - September 2019


•    North Ramp Rehabilitation

Construction completed.

•    Construct Taxiway E Extension

Construction completed.

•    Airport Security Improvements

Work is underway and should be completed by November 2019.

•    Rehabilitate T-Hangar Buildings

Repair of several hangar doors should be underway by October 2019.

•    Construct MRO Hangar

Negotiations with the successful proposal for a 30,000 sf hangar are underway.

•    Reconstruct Center Apron

Grant funding is in place and the design is underway for this project. Estimate start of construction: May 2020 (after the Vero Beach Air Show).

•    Rehabilitate GA Apron

Grant received for this project; design should begin in October 2019.

•    Construct Natural Gas Pipeline

Grant received for this project; design underway, construction should begin in October.

•    Rehabilitate Southwest Apron

Planned for late 2020, pending grant funding.